Conversion of existing warehouse into a data storage facility
Acton, London
Diamond saw cut and install piling mattress for 182 reinforced piles, cut down piles and form pilecaps with holding down assembly to carry 10,296m2 of 150mm thick concrete mezzanine floor including disposal of contaminated / toxic excavated material.
Structural engineering works included:
| Main Contractor: | Underhill Engineering |
| Architect: | Househam Henderson |
| Structural Engineer: | Scott Wilson |